County schedule for Point Dume rock dumping avoids high tides
Heavy equipment will rebuild the Point Dume revetment during evening low tides, with work paused for the coming storm and Thanksgiving.
By Hans Laetz
The dumping of gigantic rocks along the road at Point Dume continues, and now the county is giving a schedule of which hours its heavy equipment will operate. The rock placement can only be done during low tides.
L.A. County Beaches and Harbors is trying to fortify the rock fortress it's building to protect the road, the parking lot, and the lifeguard headquarters down at Point Dume. Heavy trucks are bringing in boulders — much larger rocks than the small ones that the county dumped on the beach two months ago.
Those rocks basically got pushed around by the large surf in early September and October. They were entirely useless.
The entire revetment has to be redone, with bigger rocks being trucked in from inland quarries.
The heavy construction equipment can only operate during low tides. Wednesday that window is from 1 p.m. until 11:30 p.m. On Thursday it slides back one hour, to 2 p.m. to midnight.
Work Monday and Tuesday is canceled due to the anticipated rainstorm. Wednesday and Thursday of next week the work will start at around 6 p.m. and last until about 2 a.m. No work is scheduled over the Thanksgiving holiday.
Vehicle access is blocked from the Sunset Restaurant down to the Point. The restaurant and Birdview Drive do remain open.
Pedestrians and cyclists are prohibited from entering the active construction areas while equipment is moving around.

Comments (0)· Be the first to comment.